How to run a project reset day
Picture a monthly status report that says the project will finish in January and that the slip is recoverable, while the schedule the planner keeps says March. Both go to the same steering committee, and nobody puts them side by side, because the report is written to be read and the schedule is written to be used. What helps a team in that position is one day where the people who run the project agree where it stands, and then sort what they can fix themselves from what has to go upward with options attached.
That day is a project reset. Below is the method behind our Project Reset Workshop, written so you can run the day yourself.
When a reset is the right call
The clearest case is a project slipping on scope, schedule or cost, where the reported position and the measured one have drifted apart. The same day works before a kickoff or a gate review with two changes: the opening reality check tests whether the plan is ready (logic, budget phasing, how progress will be measured) instead of comparing plan with actuals, and the closing session compares delivery strategies instead of recovery options.
Check for the cases where it is the wrong tool before anyone books a room. A reset assumes the project is worth finishing, and whether it should be stopped is a board question for a different setting, as the piece on why failing programs keep running argues. A slip that is mostly a live claim or a commercial dispute is a poor fit too, because those topics have to stay out of the room and the day would end up planning around its main problem. The day also depends on a sponsor who agrees to come back at the end and decide what is theirs to decide; if that commitment is missing, settle it before you set a date.
People and data
Keep the room to 12 people or fewer from the project itself: the project manager, the planner, the commercial or contracts lead, the site or delivery lead, the engineering lead, whoever runs project controls, and the main contractor’s project manager if the relationship can take it. If cost figures are sensitive in a mixed room, keep cost data to the owner’s team and measure progress with a budget-weighted percent complete.
The sponsor opens the day briefly, says what they want to decide at the end, and leaves until the late afternoon. Without them present, the team can argue about facts without managing how each one will sound upstairs. Agree this with them on the scoping call, weeks ahead, along with what they expect to decide when they return.
Ask for the data at least seven working days ahead, as extracts with personal names replaced by roles and with anything under a third-party confidentiality agreement or a live claim taken out:
- The current schedule with its baseline, forecasts, predecessors and float, at summary level.
- Cost and progress by work package: earned value if it is tracked, otherwise budget, actual cost and percent complete.
- The last two monthly status reports and the notes of the last four weekly progress meetings.
- The risk register or RAID log as it stands.
- The scope documents and the change or variation log.
- A stakeholder list by role, with how often each one hears from the project.
- Board or steering committee terms, the delegation of authority, and the list of regular meetings and reports.
Where data is missing, write “no data” on the sheet on the day and add a 30-day action for whoever should hold it.
The shape of the day
Facts come in the morning and fixes in the afternoon, and nobody proposes a recovery until the room agrees where the project stands. Every exercise runs brief, work, test, debrief, with a second group testing the work against the source data. If you run late, drop the root cause step in the risk exercise first, then the stakeholder two-by-two in the decision rights exercise, then any second round of debrief questions. Never cut a test or the 30-60-90 actions.
Start with a reality check. First, each person writes on a sticky note the date they honestly think the project will finish, face down. Groups then work out how much has been done against plan and what it cost (earned value over planned value for schedule, earned value over actual cost for cost), compare forecast milestones with the baseline, and list every statement in the last status report the numbers do not support. Then the sticky notes go on a timeline beside the official forecast.
Scope comes next: sort deliverables into in, out and disputed, and write acceptance criteria someone could pass or fail. Then walk the critical path backwards from the end date. The GAO’s Schedule Assessment Guide defines it as “the path of longest duration through the sequence of activities”, and a schedule with missing links will show you the wrong path. Look hardest at external dependencies with no promised date.
After lunch, run a pre-mortem, the technique Gary Klein described in Harvard Business Review and listed on our Insights page: the team assumes the project has already failed and writes down why, silently first, with the most senior person speaking last. Use the results to triage the RAID log and agree the top five. Then map decision rights, with exactly one accountable role per decision. Slow decisions hold up the critical path as surely as slow work, the argument of an earlier piece on unmade decisions. The last fix is governance: stages, tolerances, and a rule that escalates on forecast, the way PRINCE2’s exception report reaches the board before an overrun happens.
When the sponsor returns, groups present re-baseline options built from four levers: accept the slip and re-baseline, add resources to critical activities, overlap activities planned in sequence, or reduce or phase scope. The sponsor says aloud what they can decide today and what goes up.
The team leaves with a one-page reset plan. The page records where the project stands (measured progress, an estimate at completion labeled as an estimate, baseline against forecast end date, the corrected critical path), what was agreed on scope, risks, decision rights, governance and meeting cadence, and the options with team-estimated dates and costs. It keeps apart what the sponsor decided on the day and what still needs a decision elsewhere, with who makes it and by when. Below that sits a 30-60-90 day action table where each action has one owning role, a due date and a line describing what done looks like. It closes with a few measures, each with today’s value, a 90-day target and the role that counts it. Within three working days the facilitator types the wall photographs into a written record for the sponsor: the reset plan as its cover, then the scope statement, risk register, RACI, governance charter and communication cadence.
Rules that protect the day
If someone senior announces a recovery plan before the facts are on the wall, write it up as one more option and test it like the others. Give every action one owning role, because an action owned by a group has nobody to chase it, and keep the first 30 days to eight actions or fewer, since a long list gets done less. Label option dates as team estimates, since only the board can approve a re-baseline. Put roles on the wall instead of names, and never record who said what. Book a 45-minute call for 30 days later with the sponsor and the plan owner when you first agree the date, and read that date out at the close. The call checks the 30-day actions one by one.
To judge whether your own project needs a reset, use the project reset readiness check: ten yes or no questions and the data pack on one page.