The government that budgets for its own optimism
In the second week of December a sponsor asks two people when the new billing system will go live. The first says September. The second says September holds if the vendor delivers the interface by May and the data migration rehearsal passes the first time, and that without those two things the realistic date is closer to Christmas. The sponsor has a board paper due on Friday with a box in it marked go-live date, and September goes in the box. The second answer was at least as well informed as the first. It also came with two conditions the sponsor would now have to track and answer for.
When September slips, the usual diagnosis is a poor estimate, and the usual cure is a better one: more detail in the schedule, a more senior estimator, contingency added once the slippage shows. All of that treats the overrun as a surprise. It has been a predictable event for decades, and at least one government has put that in writing, with numbers.
A correction published in advance
HM Treasury’s supplementary Green Book guidance on optimism bias, dated 21 April 2013 on gov.uk, tells UK central government appraisers to adjust their first estimates of cost and duration upward before using them, on the stated grounds that estimators are systematically optimistic. How large the adjustment is depends on the kind of project, and the guidance publishes a range for standard and non-standard buildings, standard and non-standard civil engineering, equipment and development, and outsourcing. For works duration, the upper bound is 39% for non-standard buildings and 54% for equipment and development, and the lower bounds for the same two categories are 2% and 10%. Those percentages are added to the duration estimate at the outset of appraisal, and they come down toward the lower bound as specific risks are identified and priced, so a project team earns a smaller adjustment by showing its risks, which is a different thing from asserting confidence. They describe a correction to an estimate, so neither figure is a measured overrun or a share of what the project finally took.
The Treasury table rests on 50 projects; the research that confirms its direction rests on decades of them. Bent Flyvbjerg’s research on megaprojects, drawing on roughly 70 years of comparable data across many countries and project types, finds that nine out of ten run over on cost, with no improvement across the period measured. An earlier piece here on what published AI failure rates actually count drew on the same research for a different purpose. For anyone setting a date, the relevant part is plain: the error has a known direction. A government that knows which way its estimates will be wrong, and roughly by how much, can correct them before anyone announces a number, and the Treasury chose to.
The table itself is weaker than its official standing suggests. By the guidance’s own footnote, its uplifts come from a single 2002 Mott MacDonald study of 50 completed UK public procurements, and coverage of some categories is thin. Evidence that Flyvbjerg and colleagues gave the Edinburgh Tram Inquiry in 2018 argued that the uplift applied in practice came out smaller than the data justified, and that the Green Book and the separate Transport Analysis Guidance apply their baselines inconsistently. An uplift can also become a number to bargain over, trimmed in review until the adjusted date looks like the one the sponsor wanted in the first place. Two of these say the correction is probably too small. The other two say it is too rough to trust category by category.
How the announced date gets chosen
So why does the date that leaves most planning meetings still carry no adjustment? The answer is in the opening scene. A plain date is easy to use: it fits the box and can be repeated to a board without a footnote. A conditional date gives the sponsor work, because someone now has to watch the vendor’s May delivery and the migration rehearsal and explain the date if either goes wrong. A sponsor with a Friday deadline picks the answer that is cheaper to carry, and the person who gave it earns a name for being clear. Whether September turns out to be true plays no part in a choice that is made in December.
Dates set in December often fail after the sponsor or the estimator has changed jobs. The sponsor who wrote September in the box is elsewhere by the autumn, and whoever inherits the slipped date never heard the answer that came with conditions, so nothing in the organization connects the miss to the choice that produced it. Where the same two people do work together for years, a sponsor who has been burned once will read the next confident date from that source with some suspicion, and that correction is real. It depends on a continuity that most portfolios lack.
What the Treasury did was take the choice out of the meeting. The adjustment is applied to the first estimate by rule, before anyone has to decide how confident to sound, so the adjusted figure reaches the box without a person having to argue for it.
Setting next year’s dates
Whoever signs off next year’s dates has two ways to copy the move. One applies an uplift by project type to every first estimate, which is quick, though a table built on 50 UK public projects says little about a system migration. The other lets a date leave the team only with the conditions it depends on written beside it in the board paper, along with the date that applies if they fail. Each condition needs an owner and a point in the year by which it is known to hold or not, so that the interface delivery is confirmed or missed by mid-May and the sponsor learns in spring whether September still stands, while there is time to act on it. A pre-mortem, one of the models on our Insights page, finds those conditions by having the team imagine the date already missed and work backward to the causes.
The second is the one to choose. It costs a longer board paper, and in return the sponsor owns the conditions in December instead of discovering them in August. When a date slips anyway, a project reset day is one way to set a new one, with its conditions attached.