Four AI jobs for project managers, and the check for each
A project manager pastes a month of meeting notes into a chat tool and asks for the status report. What comes back is tidy and easier to read than last month’s. One line says the client has approved the design. The notes say the client approved one package of drawings and that the rest is still waiting. Nobody spots the difference, the report goes to the steering committee, and a week later the wrong sentence sits in other people’s slides. A status report gets forwarded, which is why a fluent error in it travels further than one in any other project document.
Two stories circulate about these tools. In one, the tool drafts the plan and the report for you. In the other, it is a toy that invents things and belongs nowhere near delivery work. Both skip the question a project manager can answer: for a given job, can the output be checked against data the project already holds? Where it can, the tool earns a place, and where it cannot, the project manager has no way to tell a sound draft from a well-written guess.
Checking has a cost, and on some jobs it eats the whole saving. If tracing every line of a draft back to its source takes as long as writing the thing by hand, the tool has not paid for itself on that job, and the honest move is to drop it there. Some organizations allow no AI tools at all, or block them on company laptops. Then the right step is to wait for a policy, help shape it by writing down which tasks you would want approved and which checks would go with them, and keep company data out of personal accounts in the meantime.
With those limits stated, four everyday jobs pass the test: planning, risk, reporting and stakeholder updates. They are the first four exercises in our AI in Project Delivery session, and the skill each one teaches is the check.
Planning and risk
On the plan, the tool is quick at listing what looks missing from a set of activities and at running mechanical tests when you give it the rules: activities past their finish date and not complete, progress recorded out of sequence, activities with no successor, progress in the notes that disagrees with the plan. It is weak at anything that needs data it was never given, such as realistic durations, local permit rules or what the contract says. So the prompt carries a data date and its rules: use only the data supplied, write “cannot tell from the data” where a point cannot be judged, and mark any standard, regulation or typical duration “to verify”.
The check is a person with the plan open. For every finding, the checker finds the line that proves or disproves it and marks it confirmed, wrong, or cannot tell. A quoted standard or a “typical” duration goes into a box marked “needs a source”, and nobody uses it until someone has found one. Reading the plan yourself before opening the tool, and noting what looks wrong, gives you a control list to compare against the tool’s.
The risk register is where vague entries become usable ones. Nobody can act on “Weather” or “Resources”. Rewritten in a cause, event, effect form, a risk becomes something an owner can work on, and the tool does that rewrite fast. The prompt tells it to keep the probability and impact ratings exactly as they are and to add no numbers, owners or dates that are not in the source. A tool can break that rule even when told, so the check lays the original register beside the rewrite and goes line by line. Did a rating change? Did an owner or a date appear from nowhere? Does the new wording still describe the same risk, and could the project actually carry out the suggested response? The score stays the team’s judgment, and the risk owner approves the new wording before it goes in. One follow-up prompt is worth keeping: ask which threats to the key date are missing from the register, and treat the answer as a list to test with the team. It works like a short pre-mortem, one of the entries on our Insights page, where a team imagines the project has already failed and works backward to the causes.
Reporting and stakeholder updates
Reporting saves the most time and carries the most risk when nobody checks it. Four rules in the prompt turn a draft you would have to rewrite into one you can check. Put the source in square brackets after every sentence that contains a fact. Where the notes and the plan disagree, show both values and mark the conflict. Calculate no new forecast date; say the planner will update it. Leave the status color blank.
The check is a trace test: next to every sentence with a fact in it, the checker writes the source, which is a note, a plan activity or “none”, and every “none” gets fixed or deleted. The session’s practice notes carry planted inconsistencies for this step, a partial approval like the one in the opening among them.
For stakeholder updates the prompt carries a short list of facts, and the tool drafts the news for two readers: a client director who wants facts first and a decision to make, and a neighbor who only cares about noise, traffic and power interruptions. Nothing goes into either message unless it is on the list. The check is a fact table across both versions plus a hunt for promises. Every “we will”, “no impact” and “on track” either traces to the list or comes out.
Who owns what the tool produces
All four checks assume one thing is settled first: whose name is on the output. The person who signs the plan, the report or the email owns every word in it, whoever drafted it. Some decisions stay with a person however good the draft looks: safety calls, contractual and commercial commitments, anything that affects someone’s career, anything using personal data about an identifiable person, and anything that leaves the organization under someone’s name. A forecast date sent to a client is a commitment, so a person checks it in the scheduling tool and sends it. In the session, teams sort decision cards into three columns (the tool drafts and a person checks, the tool helps and a person decides, the tool stays out) and have to agree on every card. The “stays out” list becomes the guardrails of a one-page adoption plan with one named owner.
The order matters. One study of workarounds, by van der Waal and colleagues, defines a workaround as a goal-directed deviation from a standard process undertaken to complete work. Apply that to a team handed a tool with no agreed check and no agreed owner. The reports still go out, and whatever the team improvises to get them out is recorded nowhere. When a wrong sentence then reaches the steering committee, nobody can say whether the tool failed or the process did, since no process was agreed. Settling ownership and the check before deciding how far to lean on the tool puts the people and the process ahead of the tool, and a team that works in that order can tell a tool limitation from a failure in its own process. How to run a project reset day gives every action one owning role for the same reason, and the earlier piece on the gap between an AI pilot and a rollout covers what happens when nobody owns the handoff.